The Hrobice Drinking Water Treatment Plant was built in 1959. After its modernization in 1997, the plant was designed to supply drinking water for Pardubice, Lazne Bohdanec and other nearby towns and villages. It is also a reserve source of drinking water for the city of Hradec Kralove. The treated water is pumped into the water reservoir at Kunetice Mountain and then distributed to the customers. The operator of the plant is Vodovody a kanalizace Pardubice, a.s. (hereinafter VaK).

Hrobice Drinking Water Treatment Plant main control room
In 2002, GEOVAP, spol. s r.o was chosen as the supplier of a SCADA-based control system for the Hrobice Drinking Water Treatment Plant. The previous control system did not meet the requirements for a modern control and visualization system. Therefore, it was necessary to develop a new communication driver for reliable communication between the existing Sauter WSR3000 PLC devices and the Reliance SCADA system.
Thanks to the implementation of the Reliance system, communication between the main control room and PLC devices is now much faster. The treatment process is monitored from both the Hrobice main control room and the remote work station at VaK. The operation data is archived for analysis or further processing. The new visualization also allows monitoring and control of pumping raw water from remote sources (flooded sandpits Oplatil and Ceperka).

Tanks for water treatment using sand filters
"During modernization, the plant was equipped with the Sauter WSR3000 PLC devices, which is a Swiss system. Unfortunately, soon after the test operation, the supplier stopped supporting the system and sold it to the Rittmeyer company. The problem was that we had Sauter WSR3000 PLC devices that provided communication only in default settings. Also, our previous SCADA software was running in obsolete MS-DOS, that wasn't user-friendly enough. Therefore, VaK announced a tender on the suppliers of the communication and visualization (SCADA) software. The winner of the tender was the GEOVAP company, which offered a complete solution of the problem. The GEOVAP company developed a new communication driver for reliable communication with Sauter WSR3000 PLC devices and implemented the Reliance SCADA/HMI system. This system provides control and visualization of the entire treatment plant. Reliance also provides communication with the VaK control room located in Pardubice. Currently, we are going to connect the water sources to the treatment plant LAN via Ethernet because this feature is supported by Reliance."
Ing. Jaroslav Kubinek, business manager of VaK Pardubice, a.s.
Pumping of raw water from flooded sandpits
Filtering of raw water
Filtering and machine room
Machine room - water treatment


Country
Czech Republic
Name
Modernization of the control system for the Hrobice Drinking Water Treatment Plant
Implemented by
GEOVAP, spol. s r.o.
Date
2002
Control System
29x Rittmeyer WSR3000
Software
1x Reliance Runtime Control with 1,000 data points
1x Reliance Runtime View with 1,000 data points